Bringing Back Power a Slow, Tricky Process
Electricity in Demand
Inability to store electricity part
of complex challenge Rolling blackouts likely to persist
over weekend. When electrical power fails as it did
Thursday afternoon across a large swath of Ontario and the northeastern
United States, it can take days to restore and large cities, like
Toronto, are usually among the last to regain service.
"We're now expecting it to take until Monday
(to get power fully restored in the city)," said Karen Evans,
a spokesperson for Toronto Hydro, the local utility that
supplies 655,000 customers in Canada's largest and most demanding
power market.
By late yesterday afternoon, the city had regained
between 80 and 90 per cent of normal service, but isolated pockets
remained in the dark, and rolling blackouts meant some areas
that had electricity lost it for up to two hours.
The city began receiving limited emergency supplies
of electricity on Thursday night around 10 p.m. for use
by essential services such as hospitals, police, fire and ambulance
stations, and water treatment plants, she said.
Homes and businesses connected to lines serving essential
services also got service just because they happened to be on the
route, Evans said. But service was fleeting in cases as some areas
that initially got power later lost it, she said. "As people
woke up (yesterday) morning and started turning on their lights,
more power was demanded. We couldn't meet the demand so we had outages,"
said Evans.
In other cases, Toronto was forced to give up supply
to meet demand in other parts of the province, another Toronto Hydro
spokesperson, Blair Peberdy, explained late yesterday.
Rolling blackouts, as they're called, are expected
to persist over the weekend as the Independent Electricity Market
Operator, which manages the grid across the province, continues
to adjust the supply to meet demand. The blackouts shouldn't last
more than about two hours, Peberdy said.
Areas considered essential are less likely to get
hit, Peberdy said. They include hospitals and other emergency services
such as fire, police and ambulance stations, followed by critical
municipal services, such as water pumping stations, then the Toronto
Transit Commission, and finally major office towers and shopping
centres. Downtown is given priority.
But Toronto Hydro is just one piece of the puzzle.
When it comes to restoring power, a huge part of the challenge comes
from the nature of electricity itself, experts said.
Think of electricity as a commodity
that is manufactured, much like steel or lumber. But unlike other
commodities, electricity can't be stored. It's produced at the very
instant when it's needed. The lines that transmit power across the
province serve as a dedicated point-to-point delivery system. Demand,
or load, must be perfectly balanced with supply, or generation,
or there's trouble — quick.
Most electrical systems operate on alternating current,
which must be maintained at a constant speed of 60 Hertz, or 60
cycles per second. If demand exceeds supply it's like flushing a
toilet while taking a shower — the flow of electricity
slows. If supply exceeds demand, the flow speeds up.
Few electrical appliances can tolerate even small
variations, leading to fried computers, fridges and power generating
equipment. That's why most transmission systems are designed to
protect electrical equipment by disconnecting generators from the
grid when demand and supply get too far apart, said Tom Adams, executive
director of Energy Probe.
"If they don't, there will be damage to
the system and they won't be able to bring it back even in 24 or
36 hours," said David Drinkwater, energy consultant and former
chief economist at Ontario Hydro.
In fact, an imbalance in the system is what caused
Thursday night's blackout in the first place, experts agree, though
no one can agree on where or how the upset began. All that's certain
is that once the problem started it "cascaded" through
the vast interconnected transmission systems that serve most of
Ontario and the northeastern U.S., knocking out service to some
50 million people.
Once a massive failure has occurred, getting power
back up from a "black start" is a tricky business, experts
said.
First, Ontario has to be isolated from the other
states and provinces that share the northeastern grid. Then specific
communities are isolated from the rest of the province because power
must be restored gradually to keep supply and demand in balance.
It starts with the handful of generating plants that
have their own backup power. The rest join the grid after power
begins humming along the transmission lines. The last to come on
line are the nuclear generating stations since restarting them is
a technologically trickier process. Ontario's nuclear stations account
for up to 25 per cent of the province's supply
Initially, power is added in very small increments,
as little as 10 megawatts every 10 minutes, a pace Adams called
"glacial" for a system that was running 24,000 megawatts
when it shut down.
As supply is increased, it must be matched by demand.
At first, that might mean a single row of streetlights is added,
then a neighbourhood, then a small community. There's little room
for error and lots of potential for setbacks, experts said.
"I would compare it to being parked beside
the 401 and having to go from a dead stop to full highway speed.
You've got very little tolerance depending on whose fenders you
want to bounce off," said Drinkwater.
Toronto is one of the last to get service because
it is so large, said Toronto Hydro's Evans.
"We don't have priority because of the
balancing issues. When you only have so much power available, you
tend to target the areas of lower demand because excess demand is
what causes failure," Evans said.
The supply of electricity in Ontario involves a number
of players, including Ontario Power Generation, which runs most
of the generating plants, and Hydro One, which operates most of
the transmission lines that run between cities.
Overseeing it all is the Independent Electricity
Market Operator, commonly called the IMO, which acts like a broker
or middleman. It doesn't own any facilities but is responsible for
matching supply with demand.
The non-profit organization decides when and how
much power each part of the province, including Toronto, will receive.
In an emergency, supply is distributed based on need, said Toronto
Hydro's Evans. Carefully worked-out protocols determine who's first
in line, Evans said. The IMO has so far refused to make this information
public.
However, when Toronto Hydro officials realized Thursday
night that the city was too far down the priority list to maintain
its essential services, it appealed to the IMO for help.
"The IMO recognized we have essential
services in the city, so we got power earlier than we expected,"
Evans said.
by Dana Flavelle and Madhavi
Acharya-Tom Yew
Energy Probe
|